VIIVX is a purpose-built instability detection system that helps renewable generators meet the latest grid connection requirements, without adding complexity to your site.

Why Instability Detection Matters

As more renewable generators connect to the grid, network service providers are tightening their requirements around forced oscillation and instability detection. Under NER clause S5.2.5.10, generators are increasingly required to demonstrate real-time detection capability as a condition of connection.

TransGrid, VicGrid and Powerlink have each released their own requirements under this clause, and more NSPs are expected to follow. For generator owners, that means instability detection is no longer optional. It is fast becoming a standard part of getting connected and staying connected.

EPEC Technologies VIIVX product was designed in-house to meet these requirements directly, drawing on our own experience delivering grid connections and commissioning across the National Electricity Market.

compliance & nsp support

Built to Meet Australian Grid Connection Standards

VIIVX is designed to align with instability detection requirements under NER clause S5.2.5.10 as they are released by Australian network service providers. Powerlink’s requirement also calls for an external high frequency recorder alongside the instability detection system.

Grid Connection Expertise

Developed using EPEC's own experience across grid connections, commissioning and SCADA integration.

Advanced Detection Algorithm

Uses multi-mode decomposition to accurately separate forced oscillations from background noise, with fully configurable detection thresholds.

Matched to NSP Requirements

Built specifically to align with the requirements of Australian network service providers under NER clause S5.2.5.10.

Compact, Reliable Hardware

Powered by a robust Bachmann controller, designed to integrate easily with existing site SCADA.

What VIIVX Delivers

VIIVX combines accurate detection with straightforward integration, so it fits into your existing site without adding operational complexity.

Play Video

Download the VIIVX Data Sheet

Get the full technical specifications, integration details and environmental ratings for VIIVX in one document.

If you’re scoping a new generator connection, instability detection is quickly becoming part of the approval process rather than an afterthought. Building it in early means one less thing to resolve later in the connection study, and one less risk to your commissioning timeline.

VIIVX is designed to sit alongside the rest of EPEC’s grid connection and commissioning work, so if we’re already involved in delivering your project, adding VIIVX doesn’t mean bringing in a separate vendor or managing another set of specifications. It’s built by the same team that understands your connection requirements from the outset.

Whether you’re planning a new connection or need to meet updated NSP requirements on an existing site, our team can talk you through how VIIVX fits into your project and your timeline.

Testimonials

As we approach the end of the year, I wanted to take a moment to thank you all for your outstanding support throughout 2025. Your contribution was instrumental in completing the November testing activities, and your technical insights significantly s...
Read more..
PCL - Logo - EPEC Group
We wanted to take the opportunity to recognise your team’s exceptional performance over the past year at Stubbo. Setting aside opinion and focusing purely on facts:From the start of Hold Point and Staging testing, every single Hold Point was comple...
Read more..
GPG - Logo - EPEC Group
EPEC Group has been a key delivery partner for Global Power Generation across several major renewable energy projects in Australia, demonstrating a strong commitment to collaboration, innovation, and delivery excellence. At Bundaberg Solar Farm, a 10...
Read more..
Just a quick message to say how impressed I am with Jesus & Thiyagu. Their experience and know how were invaluable to us on site here in Mulwala SF. Also, a tip of the hat to working through some pretty tough heatwave conditions. Very pleased wit...
Read more..
BEON - Logo - EPEC
Beon and EPEC have worked closely together on a site-specific HIL pre-commissioning for a large solar project Beon was constructing, which has been successful in mitigating several key risks before the commissioning and testing phase of the project. ...
Read more..
Over the last two years, UQ has closely collaborated with EPEC Group to bring HIL from academic activities in the university laboratory to successful industry implementation. New modelling and systematic testing procedures have been established, and ...
Read more..
The EPEC team are innovation leaders in the Australian energy sector, actively supporting complex grid integration and renewable asset commissioning. EPEC Group has played a pivotal role in positioning real-time simulation as a standard delivery tool...
Read more..
PCL - Logo - EPEC Group
EPEC delivered the substation works on the Gunsynd project to a high standard, with strong quality of build and reliable onsite support. Their team were professional, collaborative, and solution focused through the delivery.
Read more..
PCL - Logo - EPEC Group
Congrats to the entire EPEC team for this critical milestone. Chris and the team decided to miss PCL event to complete a PCL milestone, much appreciated.
Read more..
PCL - Logo - EPEC Group
Hi EPEC team, Just want to applaud you for your efforts in bringing substation to energisation. It was my first time working with EPEC and when things were not looking promising earlier this year, everyone at PCL gave me confidence that we will get t...
Read more..